www.chinaservicesinfo.com

News and Policies

500kv submarine cable laid between Zhoushan and Ningbo

Updated: Nov 22, 2018 chinadaily.com.cn Print
Share - WeChat

到达.jpg

The first domestic-made 500-kilovolt submarine cable reaches Dapengshan Island, Zhoushan, on Nov 20 after a six day laying operation under the East China Sea from Zhenhai district, Ningbo. [Photo/wifizs.cn]

The first domestic-made 500-kilovolt submarine cable reached Dapengshan Island, Zhoushan, on Nov 20, after a six day operation laying the cable under the East China Sea between the city and Zhenhai district, Ningbo, Zhejiang province. 

The cable, developed by the State Grid Zhejiang Electric Power Co and related national research institutes and cable manufacturers, is also the world's first 500-kilovolt cross-linked polyethylene insulated submarine cable. 

To ensure the smooth installation of the cable, the State Grid Zhejiang Electric Power Co built a 5,000-metric-ton submarine cable construction ship Qi Fan 9, the first of its kind in China, and conducted multiple trial voyages before the cable installation. 

As part of the city's 500-kilovolt power transmission project, the successfully laid 17-kilometer cable marks that the project has entered a critical stage. 

The project, designed to build a 500kv power transmission channel between the city and Ningbo, will help strengthen the power supply for the development of Zhoushan Archipelago New Area and contribute to the construction of the Belt and Road Initiative when entering operations.

启帆9.jpg

Qi Fan 9, a 5,000-metric-ton ship developed by State Grid Zhejiang Electric Power Co, helps to lay the cable on the East China Sea. [Photo/wifizs.cn]

工人敷设.jpg

Workers install the cable on Dapengshan Island, Zhoushan on Nov 20. [Photo/wifizs.cn]

Copyright©2024 China Daily. All rights reserved.

京ICP备13028878号-6

京公网安 京公网安备 11010502032503号